Great River Energy, wholesale electric supplier to Stearns Electric Association, is planning to build approximately two miles of new 115,000-volt (115-kilovolt) overhead transmission line in Bruce Township, in southern Todd County. The transmission line is needed to enable Stearns Electric Association to maintain the reliability of their existing Pillsbury Substation to be able to reliably serve their members’ electrical power needs.

This project will include the construction of approximately two miles of transmission line from the Pillsbury Substation, which is located at the southwest corner of the intersection of Grosbeak Road and County Road 105. The proposed route travels south approximately two miles along County Road 105 where it will connect to an existing transmission line operated by Minnesota Power.

Quick facts
  • Notifications: Fall 2024
  • Project permitting: 2025-2027
  • Survey/design: Spring 2027-Summer 2028
  • Easements/environmental permits: Spring-Winter 2027
  • transmission line construction: Spring-Fall 2028
  • Energization: October 2028
Schedule
  • Lwngth
    Approximately 2 miles
  • Voltage
    115-kV
  • Structures
    Wood poles
  • Spans
    350 to 400 feet apart
  • Right of way
    100 feet wide (50 feed each side of center of pole line)
Project Contacts
Anson Belcourt
Great River Energy
Phone: 763-349-0081
Mark Strohfus
Great River Energy
Phone: 763-445-5210