Great River Energy proposes to build and operate approximately 8.75 miles of new 41.6-kilovolt (kV) overhead transmission line in southern Otter Tail County to provide power to the new Lake Region Electric Cooperative distribution substation.

Quick Facts

Transmission line length: 8.75 miles
Voltage: 41.6 kV
Structures: Single wood poles
Span length: 280 to 400 feet apart
Right of way width: 70 feet, 35 feet on each side of the transmission line.
Permits: US Army Corp of Engineers, MN Department of Natural Resources, Otter Tail County Highway Dept.



View Map & Fact Sheet

Public meetings

Representatives of Great River Energy and Lake Region Electric Cooperative held an open house meeting on Feb. 23, 2016, at the Maine Township Hall and provided information about the proposed project and listened to landowners.

Schedule

Easements

Summer 2016 to Winter 2016

Construction

Originally scheduled for Winter 2016 to Spring 2017. Due to permitting delays, construction timeline is to be determined.

Restoration

To be determined

Other Info

Project is expected to be placed in service in 2018

Project Contacts

Dan Lesher
Senior Field Representative
763-445‐5975
dlesher@grenergy.com

Marsha Parlow
Transmission Permitting Analyst
763-445-5215
mparlow@grenergy.com

Media Contacts

If you are with the media, please contact:

Jennifer Mattson
jmattson@grenergy.com
763-445-5722
Twitter: @jennymmattson

Lori Buffington
lbuffington@grenergy.com
763-445-5714
Twitter: @lbuffing