LeSauk and St. Wendel substations and 115-kV transmission line

The St. Wendel Substation portion of this project is on-going; all other portions of the project have been completed. To meet increasing demand for electricity in the townships of LeSauk, St. Wendel, St. Joseph, and the cities of Sartell, Waite Park, St. Joseph and St. Cloud, Great River Energy and Stearns Electric Association have proposed an upgrade to the electric system in the area. The proposed project includes Great River Energy building approximately 2.4 miles of 115-kV transmission line to serve two distribution substations: the existing LeSauk distribution substation (which was upgraded in 2010) and a new St. Wendel distribution substation yet to be built by Stearns Electric Association.

The three major components to this system upgrade are listed below.

  • LeSauk to St. Wendel 115 kV transmission lines
  • Upgrade of LeSauk substation
  • New St. Wendel substation

Public meetings

Currently there are no open house meetings scheduled for this project. If you have any questions, see contacts below.

Schedule

Easements

June 2016 to November 2016

Construction

Construction of the St. Wendel Substation will occur spring 2017 to fall 2017
Construction of the 115 kV line connecting the LeSauk Substation is complete.

Restoration

Restoration around the line connecting the LeSauk Substation is complete.

Other Info

St. Wendel Substation to be energized November 2017.
The LeSauk Substation has been energized.


Permitting/Environmental Approvals

All permits and approvals have been received from Stearns County.

Project Contacts

Rick Heuring
Senior Field Representative
Great River Energy
763-445-5979
rheuring@grenergy.com

Matt O’Shea
Stearns Electric Association
320-256-1623
moshea@stearnselectric.org

Media Contacts

If you are with the media, please contact:

Jennifer Mattson
jmattson@grenergy.com
763-445-5722
Twitter: @jennymmattson

Lori Buffington
lbuffington@grenergy.com 
763-445-5714
Twitter: @lbuffing